The ₱2.48-million water fountain and landscaping project in front of Olongapo City Hall.
By: Dante M. Salvaña
OLONGAPO CITY — A ₱2.48-million water fountain and landscaping project at Olongapo City Hall has drawn scrutiny over public spending priorities, with Vice Mayor Kaye Ann S. Legaspi seeking clearer details on its implementation, completion timeline and project cost.
Legaspi said she had repeatedly raised concerns during presentations and deliberations at the Sangguniang Panlungsod, stressing the need to prioritize long-term infrastructure projects that provide greater benefits to residents.
City government procurement records show that the project, covering a water fountain and landscaping in front of City Hall in Barangay West Bajac-Bajac, was awarded to Masterbuild Construction, owned by Joseph B. Eid, for ₱2,486,796.70.
The Notice of Award, signed by Mayor Rolen C. Paulino Jr. on November 7, 2025, identified the contractor as the Lowest Calculated and Responsive Bidder following public bidding.
Legaspi said she wrote the City Engineering Office on August 26 seeking an update on the project’s percentage of completion, implementation period, actual commencement date and target completion. She also questioned the absence of a project information billboard at the construction site.

She said residents had been asking her office about the construction’s duration and expected completion, prompting her to seek official clarification.
The vice mayor also raised concerns over the proposed ₱15.9-million acquisition of a property in Barangay Kalaklan for land banking, noting that no specific development plan had been presented during council deliberations.
She urged the city government to focus on long-term infrastructure, disaster preparedness and measures to mitigate the effects of El Niño.
City Public Affairs Office Chief Anthony Bayarong, however, defended the fountain project, describing it as part of the city’s beautification program aimed at improving the appearance of City Hall and providing a more welcoming environment for residents conducting government transactions.
Bayarong said the initiative was comparable to improvements at Marikit Park and Volunteers Park, as well as the installation of Christmas decorations during the holiday season.
He maintained that the project underwent the required processes, including City Council approval and public bidding.
On questions about the allocation of public funds, Bayarong said government programs covering social welfare, hospital services, road construction, desilting, health and education have separate budget allocations.
Regarding concerns that the project was overpriced, he said he had consulted private contractors who reportedly considered the amount reasonable.
Bayarong also suggested that political considerations had contributed to the controversy surrounding the project.